Here are the currently open tasks, to complete 2.1.1 support:

  1. Circe1 with ISR for resonance/on-shell production
  2. Circe1 generator mode
  3. Circe1 photons
  4. EPA
  5. All e-p collision setups
  6. Disable (but don't delete) Circe2

Not really in 2.1.1

  1. EWA (also w/ Circe, ISR, PDFs)

.. and

  1. Check the status of non-collinear radiation

Change History (12)

comment:1 Changed 11 years ago by Juergen Reuter

QED ISR is mostly done in r4576. Still, it has to be connected to the rest of the program for proper steering, but that should be more or less straightforward. No numerical comparison with W2.1 yet.

Next, I will go to EPA.

comment:2 Changed 11 years ago by Juergen Reuter

EPA and EWA implemented (incl. unit tests). But all (incl. mappings) has to properly connected with the rest of the program.

comment:3 Changed 11 years ago by Juergen Reuter

Owner: changed from kilian, jr_reuter to Juergen Reuter
Priority: P3P1
Status: newassigned

Next, I will do beam events.

comment:4 Changed 11 years ago by Juergen Reuter

No, at the moment I do energy scan, then beam events, the CIRCE1 and CIRCE2.

comment:5 Changed 11 years ago by Juergen Reuter

Priority: P1P3

comment:6 Changed 11 years ago by Juergen Reuter

Owner: changed from Juergen Reuter to kilian
Status: assignednew

comment:7 Changed 11 years ago by Juergen Reuter

Owner: changed from kilian to Juergen Reuter
Priority: P3P1
Status: newassigned

As discussed with WK, I will move on to this task, continuing with the beam events.

comment:8 Changed 11 years ago by Juergen Reuter

Owner: changed from Juergen Reuter to kilian
Status: assignednew

Spectra seem not to work as intended. Or I don't understand them properly. Refraining from this ticket. :((( Also I don't know how to properly translate this affects_beam variable. Lost in translation.

comment:9 Changed 11 years ago by kilian

Priority: P1P2

I don't change the severity, but to be done after current bug fixes.

comment:10 Changed 11 years ago by kilian

Priority: P2P1
Status: newassigned

Next: try to re-enable CIRCE, along the lines as discussed in WÜ.

comment:11 Changed 11 years ago by kilian

Description: modified (diff)

comment:12 Changed 11 years ago by kilian

Description: modified (diff)